NODE Update 2.10.2025
- All concrete patches are complete. 
- The gas service is on. 
- Rough in electrical inspection was passed Tuesday, Feb. 2nd. The contractor, R. Yoder, is coordinating with the city to activate the service. Once activated, they will need to have a final inspection done. 
- The contractor had the fire pit lit Thursday morning, Feb 6, using a generator. The electric for the fire pit since service was not on yet. The fire pit works great! 
- String lights are hung. 